Requirements for obtaining a work permit:
1- All papers are submitted and placed in a special application and delivered to the Building Permits Section, and a detailed report is prepared on the reality of the building and its conformity with the license granted to it.
2- The transaction is presented to the local planning committee to take a decision to grant the building a work permit to which services are intended to be delivered.
3- The transaction is transferred to the municipality accountant to collect the works permit fees as required.
4- The transaction shall be transferred to the secretary of the local planning committee to issue a works permit based on the decision of the local committee.
5- The originals of the transaction shall be preserved and recorded at the Municipality Court.
6- Registration document.
7- Modern land plan.
8- Site plan and modern demarcation.
9- A clearance from the municipality’s finances, the roofs and the area.
10- Building permit.